Cryptomine and data center firm Galaxy Digital has completed the first phase of pivoting its Texas campus towards AI and HPC use.
Key facts
- After breaking ground in July 2021, the 160-acre Helios campus started cryptomining operations in May 2022
- Spanning more than 2,200 acres, Galaxy said the campus's total approved power capacity has expanded to 1.63GW, with the potential to scale to as much as 3.6GW
- CoreWeave has committed to 526MW of critical IT load (800MW gross power) across three phases, all under 15-year leases
- Cryptomine and data center firm Galaxy Digital has completed the first phase of pivoting its Texas campus towards AI and HPC use
Summary
The company this week announced it has completed delivery of the first phase of power at its Helios data center campus in West Texas, delivering approximately 200MW of gross power, 133MW of critical IT load, to AI cloud firm CoreWeave. CoreWeave has committed to 526MW of critical IT load (800MW gross power) across three phases, all under 15-year leases. "Completing Phase I on budget and on schedule affirms Galaxy's position as an operator capable of executing hyperscale AI data center development," said Mike Novogratz, founder and CEO of Galaxy. After breaking ground in July 2021, the 160-acre Helios campus started cryptomining operations in May 2022.