Pattaya begins 3.5km road upgrade ahead of New Year
Compiled by KHAO Editorial — aggregated from 1 outlet. See llms.txt for citation guidance.
◌ Single Source
Pattaya City has launched a project to resurface approximately 3.5 kilometres of Phaniad Chang Road, aiming to improve road conditions and complete the main paving work before the New Year holiday period.
Key facts
- Deputy Mayor Manoch Nongyai chaired a project meeting at Pattaya City Hall on October 9, 2026, with representatives from the city’s engineering department and the construction contractor.
- Pattaya City has launched a project to resurface approximately 3.5 kilometres of Phaniad Chang Road, aiming to improve road conditions and complete the main paving work before the New Year holiday period.
- The official contract period runs from October 1, 2026, to January 18, 2027, although city officials said the main resurfacing work is expected to be finished ahead of New Year celebrations.
- The project covers approximately 3,477 metres of existing concrete road, with widths ranging from six to eight metres.
Summary
Deputy Mayor Manoch Nongyai chaired a project meeting at Pattaya City Hall on October 9, 2026, with representatives from the city’s engineering department and the construction contractor.
The project covers approximately 3,477 metres of existing concrete road, with widths ranging from six to eight metres.