4 min read

Compiled by KHAO Editorial — aggregated from 1 outlet. See llms.txt for citation guidance.

◌ Single Source

Thai–China rail keeps 2030 target despite 34.5-point lag

Phase 1 of the Thai–Chinese high-speed rail project is 34.509 percentage points behind its cumulative construction plan, although the Transport Ministry is retaining its target of opening the Bangkok–Nakhon Ratchasima route in 2030.

Key facts

Summary

Actual progress stands at 55.978%, compared with scheduled cumulative progress of 90.487%, according to Kampol Boonchom, chief engineer for special projects and construction at the State Railway of Thailand (SRT). The 250.77-kilometre route is divided into 14 civil works contracts.

Deputy Transport Minister Siripong Angkasakulkiat said that although overall construction remained behind schedule, the ministry believed the work could be accelerated sufficiently to meet the opening target. The project is intended to improve passenger travel and freight transport.

Read full article at Nation Thailand →