Elon Musk · Anthropic · Google · Datacenter Dynamics
SpaceXAI gears up data center in Arizona, Musk's company asserts it will have 6GW capacity
Compiled by KHAO Editorial — aggregated from 1 source. See llms.txt for citation guidance.
◌ Single Source
SpaceXAI is planning a new data center complex in Cochise County, Arizona, with Elon Musk’s firm claiming it could require 6GW of power at full build-out.
Key facts
- The company is apparently going to foot the bill for these upgrades, and will spend some $3.6 billion on power infrastructure, with work costing $500 million to be carried out to enable phase one
- The company wants to develop on two plots totaling 747 acres near the Willcox Playa, a dry lake 80 miles east of Tucson
- According to SpaceXAI’s application, the campus will eventually feature up to nine data center buildings, each measuring 493,000 sq ft (45,801 sqm)
- An application has been made, via SpaceXAI affiliate company Tombstone Resources LLC, to Cochise County for a special development permit, and a public meeting took place this week
Summary
The company wants to develop on two plots totaling 747 acres near the Willcox Playa, a dry lake 80 miles east of Tucson. An application has been made, via SpaceXAI affiliate company Tombstone Resources LLC, to Cochise County for a special development permit, and a public meeting took place this week where representatives of the company spoke to residents about its plans. According to SpaceXAI’s application, the campus will eventually feature up to nine data center buildings, each measuring 493,000 sq ft (45,801 sqm). When the compute will be available is dependent on grid upgrades being completed, SpaceXAI said.