Microsoft · Datacenter Dynamics
Microsoft files for data center campus in Floyd County, Georgia
Compiled by KHAO Editorial — aggregated from 1 source. See llms.txt for citation guidance.
◌ Single Source
Microsoft has filed for a data center project in Floyd County, Georgia.
Key facts
- In a Development of Regional Impact application submitted on October 20, the company reveals it is seeking to build a three-building data center campus on 349 acres of land at 0 Huffaker Road in Rome
- Dubbed ATL80, all three buildings will total up to 1,659,000 sq ft (154,126 sqm) of floor space
- The company estimates that the project will be completed by 2032 and will employ 150 people once operational
- Total power capacity will be 422MW and provided by Georgia Power, and Microsoft estimates that the maximum water supply required will be 13,500 gallons (51,103 liters) per day
Summary
In a Development of Regional Impact application submitted on October 20, the company reveals it is seeking to build a three-building data center campus on 349 acres of land at 0 Huffaker Road in Rome. Dubbed ATL80, all three buildings will total up to 1,659,000 sq ft (154,126 sqm) of floor space. The company estimates that the project will be completed by 2032 and will employ 150 people once operational. Total power capacity will be 422MW and provided by Georgia Power, and Microsoft estimates that the maximum water supply required will be 13,500 gallons (51,103 liters) per day.