US-based land firm Potentia Development has announced plans for a new behind-the-meter industrial park in Bowie County, Texas, for a prospective data center project.
Key facts
- The phased capacity will begin in Q2 of 2032 with 300MW, with another 200MW expected by Q2 of 2034, and a further 300MW in Q2 of 2036
- Project Big Pine will span 450 acres and is located at the TexAmericas Center
- Potentia intends to deliver power through islanded on-site generation rather than a grid connection, with initial energization targeted 20 to 30 months after a qualifying offtaker signs
- US-based land firm Potentia Development has announced plans for a new behind-the-meter industrial park in Bowie County, Texas, for a prospective data center project
Summary
Project Big Pine will span 450 acres and is located at the TexAmericas Center. Potentia intends to deliver power through islanded on-site generation rather than a grid connection, with initial energization targeted 20 to 30 months after a qualifying offtaker signs on. A permanent utility connection is being pursued separately through AEP subsidiary Southwestern Electric Power Company (SWEPCO). The phased timeline remains subject to utility Southwest Power Pool’s study processes, system upgrades, and definitive agreements.