The data center arm of Japanese telco NTT has broken ground on its campus in Chonburi, Thailand.
Key facts
- The data center developer signed a 100MW PPA with Thai electrical utility B.Grimm Power to power the campus back in January 2026, with energization expected to occur in Q2 of 2027
- NTT Global Data Centers announced on LinkedIn that the groundbreaking ceremony for the Bangkok 4 data center campus took place last week
- NTT Global Data Centers has been looking to expand its footprint
- It also revealed that Fuji Electric would be building the campus’ substation
Summary
NTT Global Data Centers announced on LinkedIn that the groundbreaking ceremony for the Bangkok 4 data center campus took place last week. It also revealed that Fuji Electric would be building the campus’ substation. The data center developer signed a 100MW PPA with Thai electrical utility B.Grimm Power to power the campus back in January 2026, with energization expected to occur in Q2 of 2027. This will be NTT’s fourth data center in the country, all of which are located within the Bangkok metropolitan area.