Google · Datacenter Dynamics
Google-linked Housebound Group files for two data center projects in Haskell, Texas
Compiled by KHAO Editorial — aggregated from 1 source + 4 references discovered via search. See llms.txt for citation guidance.
◌ Single Source
Google-linked affiliate Housebound Group LLC has filed for two data center projects in Haskell, Texas, with the Texas Department of Licensing and Regulation (TDLR).
Key facts
- Both data centers are planned for 1362 Red Creek Road in Haskell and will each see $400 million invested
- Journey 1A started construction on April 1, 2026, and is expected to be completed by late August 2027
- Journey 2A, meanwhile, will span 210,420 sq ft (19,550 sqm) and started construction on June 23, 2026, and is targeting a completion date in late October
- Permits were previously sought for the site from the Texas Commission on Environmental Quality by a company called Homebound Group LLC (as opposed to Housebound Group) in February 2026
Summary
Both data centers are planned for 1362 Red Creek Road in Haskell and will each see $400 million invested. Journey 1A started construction on April 1, 2026, and is expected to be completed by late August 2027. Journey 2A, meanwhile, will span 210,420 sq ft (19,550 sqm) and started construction on June 23, 2026, and is targeting a completion date in late October. Permits were previously sought for the site from the Texas Commission on Environmental Quality by a company called Homebound Group LLC (as opposed to Housebound Group) in February 2026.